Tuesday, August 2, 2011

Air Conditioners deflinitely needed nowadays....

 The HVAC guy has been hard at work this week.  After the vents were put in place, the units began being placed.  This is one of the 5 ton units.  There will be two of them.  One on each end of the house.  The ducts should go in later this week. A/C is definitely needed with the 110 degree days this week.
 This is either a heater unit or the smaller A/C unit for the storage area.  I couldn't tell which one.  The otuside units have not been delivered yet.
 The plumber has continued to work.  This is the plumbing for the kitchen sink.  It is interesting to see the kitchen lines are going in.  They run under the the slab and up the back wall of the kitchen.  There are lines for both the main sink area and the island. 
The workers continue to frame in the fireplace area.  The third A/C unit is seen in the floor awaiting placement.  By tonight the unit had already been put in place. 


Now we are waiting on the stone to be delivered and the electrician to start wiring.  

No comments:

Post a Comment