Thursday, June 30, 2011

A Foundation to Build On!


As the sun came up this morning, the first concrete trucks rolled in at 6:00am.  James at ACH braved the early morning and sent this picture to us.  The boom was in place and ready to start pumping.




This was the scene when I finally made it out here at 7:30 this morning. Almost all the concrete was in place and the stamped concrete people were there waiting to get started on the back porch.





By lunch, the concrete was poured.  The trucks were gone.  Finishing touches were being put on the foundation and boards were already being removed. 




The back porch has had its first color put into the wet concrete and the stamp placed to simulate flagstone.  Later, they will come back and dye the individual "rocks" to look like real stone and then seal it near the completion of the house.

The foundation is complete.  The chalklines are in place for the walls and framing starts tomorow morning!